Order No. 1920 requires long-term scenarios in regional transmission planning
The order sets scenario requirements and cost allocation procedures for long-term regional transmission planning.
Order No. 1920, issued in RM21-17-000 on 13 May 2024, requires transmission providers to conduct long-term regional transmission planning on a horizon of at least twenty years, using multiple plausible scenarios, and to adopt a cost allocation method for the facilities that planning selects.
The rule's significance for interconnection customers is indirect but large. Network upgrades identified through regional planning are allocated under planning cost allocation rules. Upgrades identified through interconnection study are allocated to interconnection customers. Where the line falls between those two categories decides whether a given reinforcement appears on a developer's cost estimate or in a regional rate base.
Order No. 1920-A, in RM21-17-001, addressed rehearing arguments including the role of states in the long-term planning process. The states' role is not decorative: agreement on cost allocation is the usual point at which regional plans stall.
Compliance filings define scenario inputs, including load growth assumptions. Those assumptions are where large load forecasts enter the planning record formally, rather than as trade press estimates.
What to watch: whether any region's compliance construct explicitly shifts a category of interconnection-driven upgrade into regional cost allocation.
Sources
- 01
Order No. 1920, Building for the Future Through Electric Regional Transmission Planning
FERC · RM21-17-000 · filed 2024-05-13 · retrieved 2026-08-08
- 02
Order No. 1920-A, order addressing arguments raised on rehearing
FERC · RM21-17-001 · filed 2024-11-21 · retrieved 2026-08-08
More from FERC
- Aug 07, 202603:47 ET
AD24-5-000 record addresses cost allocation for load co-located with generation
Comments in the docket describe rate treatment for large load sited behind or beside an existing generator.
AD24-5-0004 min
- Jul 27, 202607:47 ET
Order No. 2023 sets study delay penalties for transmission providers
The rule states penalty amounts and the study deadlines to which they attach.
RM22-14-0013 min
- Jul 26, 202610:47 ET
Order No. 2023 compliance filings set commercial readiness deposit levels
The filings state deposit amounts, site control requirements and the study stages at which each applies.
RM22-14-0003 min
- Jul 26, 202608:47 ET
How GRIDOCKET cites FERC eLibrary documents
Each claim in this publication carries a citation to a filing, order or dataset, with its accession or document identifier.