AD24-5-000 record addresses cost allocation for load co-located with generation
Comments in the docket describe rate treatment for large load sited behind or beside an existing generator.
The Commission opened AD24-5-000 to examine large loads co-located at generating facilities, following a contested amended interconnection service agreement in ER24-2172-000 concerning load sited at an existing nuclear station in PJM.
The dispute is narrow in law and wide in consequence. A load that sits at a generator still depends on the transmission system for reliability, for outages at the host unit, and for reserves. Whether it is a transmission customer, a retail customer, or something the tariff does not currently contemplate determines what it pays and who else pays for what it does not.
For a data centre executive, co-location is attractive precisely because it appears to bypass the interconnection queue. That premise holds only if the rate treatment holds. If the Commission or PJM lands on a construct that assigns network service charges to co-located load, the arbitrage narrows and the queue reasserts itself as the binding path.
For an incumbent generator, the same question determines whether existing units carry a premium as sites rather than as megawatt-hours.
What to watch: any tariff filing that proposes a defined co-location service, and whether it treats partial network service as a distinct product.
Sources
- 01
Commissioner-led technical conference regarding large loads co-located at generating facilities
FERC · AD24-5-000 · filed 2024-10-01 · retrieved 2026-08-08
- 02
Amended interconnection service agreement filing
FERC eLibrary · ER24-2172-000 · filed 2024-06-01 · retrieved 2026-08-08
More from FERC
- Aug 07, 202602:47 ET
Order No. 1920 requires long-term scenarios in regional transmission planning
The order sets scenario requirements and cost allocation procedures for long-term regional transmission planning.
RM21-17-0004 min
- Jul 27, 202607:47 ET
Order No. 2023 sets study delay penalties for transmission providers
The rule states penalty amounts and the study deadlines to which they attach.
RM22-14-0013 min
- Jul 26, 202610:47 ET
Order No. 2023 compliance filings set commercial readiness deposit levels
The filings state deposit amounts, site control requirements and the study stages at which each applies.
RM22-14-0003 min
- Jul 26, 202608:47 ET
How GRIDOCKET cites FERC eLibrary documents
Each claim in this publication carries a citation to a filing, order or dataset, with its accession or document identifier.
NATIONAL2 min