Network upgrades: the reinforcement a new generator triggers

Additions or modifications to the existing transmission system, at or beyond the point of interconnection, that are required to accommodate an interconnection request.

Network upgrades are the additions and modifications to the transmission system that an interconnection request makes necessary. They are distinguished in the pro forma agreements from interconnection facilities, which are the equipment between the generating facility and the point of interconnection.

The distinction matters because the two categories are treated differently for cost purposes. Interconnection facilities are the interconnection customer''s responsibility. Network upgrades are funded by the interconnection customer under the cost allocation rules in the applicable tariff, and become part of the transmission system owned by the transmission owner.

Upgrades identified in a cluster study are commonly shared: several projects contribute to the same constraint, and the cost is apportioned among them under the tariff''s allocation method. When a project withdraws, the upgrades it triggered are reassessed and the remaining allocations change, which is why withdrawal rules and restudy provisions are litigated as closely as the engineering.

Questions

How do network upgrades differ from interconnection facilities?
Interconnection facilities connect the generator to the point of interconnection. Network upgrades are changes to the transmission system itself, beyond that point.
Who owns a network upgrade once built?
The transmission owner, regardless of who funded it.

Sources

  1. 01

    Improvements to Generator Interconnection Procedures and Agreements, Order No. 2023

    Federal Energy Regulatory Commission · RM22-14-000 · retrieved 2026-08-09

  2. 02

    Pro forma Large Generator Interconnection Procedures and Large Generator Interconnection Agreement

    Federal Energy Regulatory Commission · pro-forma-LGIP-LGIA · retrieved 2026-08-09

Daily briefing

The dockets, read daily.

One briefing each morning: queue actions, FERC dockets, transmission and large load. Free.

Job title and region are required. They determine which segment of the briefing you receive.