Surplus interconnection service uses existing interconnection headroom
Tariff provisions describe eligibility and the study path for surplus interconnection service.
Surplus interconnection service allows a new resource to use existing interconnection capacity that the original generator does not use, typically because its capacity factor or operating profile leaves headroom. Because the injection is bounded by the existing agreement, the study burden is far smaller than a new request.
The classic application is storage added at an existing solar or wind site, or at a thermal unit whose output rarely reaches its interconnection limit. The economics are strong precisely because network upgrade exposure is small or nil.
The constraints are contractual as much as technical. The existing interconnection customer controls the headroom, site control must be arranged, and any change to the operating profile of the host resource can compress the available surplus.
For a developer without a viable queue position, this is the most reliable path to energisation on a two- to three-year horizon.
What to watch: transmission provider business practice manuals, which determine how surplus requests are queued relative to standard requests.
Sources
- 01
Order No. 2023, Improvements to Generator Interconnection Procedures and Agreements
FERC · RM22-14-000 · filed 2023-07-28 · retrieved 2026-08-08
More from Interconnection
- Aug 08, 202606:47 ET
Order No. 2023 compliance filings differ on withdrawal penalties and deposits
Transmission providers have filed cluster study frameworks under Order No. 2023. The filings set out differing deposit and withdrawal penalty structures.
RM22-14-0004 min
- Aug 08, 202606:47 ET
PJM filings set study milestones for transition cycles one and two
PJM's filings record the closure of the serial queue and the schedule stated for the first cluster cycle.
PJM-TC23 min
- Aug 06, 202610:47 ET
MISO Definitive Planning Phase assigns network upgrade cost estimates
MISO's tariff describes the study steps in which network upgrade cost estimates are produced for projects in the cycle.
MISO-DRPP-20253 min
- Aug 05, 202607:47 ET
CAISO Cluster 15 rules limit study capacity by zone
CAISO tariff revisions describe zonal capacity limits applied before projects enter study.
CAISO-C153 min