Docket
RM22-14-000
Improvements to Generator Interconnection Procedures and Agreements
- Agency
- Federal Energy Regulatory Commission
- Filed
- 2023-07-28
- Status
- FINAL RULE
- Items
- 4
Rulemaking that produced Order No. 2023, replacing serial first-come, first-served interconnection study with a first-ready, first-served cluster process, imposing study deadlines with penalties, and adding commercial readiness and withdrawal penalty requirements.
Open the filing · Order No. 2023
Coverage of this docket
- InterconnectionAug 08, 2026
Order No. 2023 compliance filings differ on withdrawal penalties and deposits
Transmission providers have filed cluster study frameworks under Order No. 2023. The filings set out differing deposit and withdrawal penalty structures.
RM22-14-0004 min
- InterconnectionJul 28, 2026
Surplus interconnection service uses existing interconnection headroom
Tariff provisions describe eligibility and the study path for surplus interconnection service.
RM22-14-0003 min
- FERCJul 26, 2026
Order No. 2023 compliance filings set commercial readiness deposit levels
The filings state deposit amounts, site control requirements and the study stages at which each applies.
RM22-14-0003 min
- FERCJul 25, 2026
Order No. 2023 compliance filings are on record; reported study timelines vary by region
Compliance filings record procedural conformity. Operator reports state study durations by cycle, with dates.
RM22-14-0004 min