Order No. 2023 compliance filings differ on withdrawal penalties and deposits
Transmission providers have filed cluster study frameworks under Order No. 2023. The filings set out differing deposit and withdrawal penalty structures.
Order No. 2023, issued in Docket RM22-14-000 on 28 July 2023, required every transmission provider to replace serial, first-come first-served interconnection study with a first-ready, first-served cluster process. The rule is uniform on structure. It is deliberately not uniform on price.
The Commission set commercial readiness requirements and withdrawal penalties as obligations rather than as fixed numbers, leaving each provider to propose deposits, site control demonstrations and penalty escalators appropriate to its footprint. Compliance filings therefore diverge on the one variable that determines behaviour: what a speculative position costs to hold and what it costs to abandon.
For a developer weighing whether to carry a position through a second study cycle, this is the whole calculation. A low-deposit, low-penalty regime preserves optionality and keeps the queue congested with projects that will not be built. A high-penalty regime clears the queue faster and raises the cost of being wrong about offtake.
Order No. 2023-A, in RM22-14-001, addressed rehearing arguments and clarified the treatment of study delay penalties applicable to transmission providers, the symmetrical obligation the Commission attached to its own deadlines. The clarification did not resolve the deposit divergence.
What to watch: the second full cluster cycle in each region, where withdrawal rates become observable rather than predicted.
Sources
- 01
Order No. 2023, Improvements to Generator Interconnection Procedures and Agreements
FERC · RM22-14-000 · filed 2023-07-28 · retrieved 2026-08-08
- 02
Order No. 2023-A, order addressing arguments raised on rehearing
FERC · RM22-14-001 · filed 2024-03-21 · retrieved 2026-08-08
More from Interconnection
- Aug 08, 202606:47 ET
PJM filings set study milestones for transition cycles one and two
PJM's filings record the closure of the serial queue and the schedule stated for the first cluster cycle.
PJM-TC23 min
- Aug 06, 202610:47 ET
MISO Definitive Planning Phase assigns network upgrade cost estimates
MISO's tariff describes the study steps in which network upgrade cost estimates are produced for projects in the cycle.
MISO-DRPP-20253 min
- Aug 05, 202607:47 ET
CAISO Cluster 15 rules limit study capacity by zone
CAISO tariff revisions describe zonal capacity limits applied before projects enter study.
CAISO-C153 min
- Aug 04, 202604:47 ET
SPP DISIS cycle assigns network upgrade responsibility
SPP's tariff describes how the Definitive Interconnection System Impact Study allocates upgrade obligations among study participants.
SPP-DRG-20253 min