InterconnectionAug 06, 2026 · 10:47 ET3 min read

MISO Definitive Planning Phase assigns network upgrade cost estimates

MISO's tariff describes the study steps in which network upgrade cost estimates are produced for projects in the cycle.

MISO studies interconnection requests through an annual Definitive Planning Phase. Requests are grouped, studied together, and assigned network upgrade responsibility. Before that point, cost figures circulating around a project are estimates without study support.

The structural feature that matters is re-study. Cost allocation within a group depends on which projects remain. Each withdrawal reallocates upgrade costs among survivors, and each reallocation can move a project across its own investment threshold. A position that pencils at the first estimate may not pencil at the third.

MISO's footprint compounds this. It spans a long north-south geography with limited internal transfer capability, so upgrade sets identified in study frequently implicate facilities well away from the point of interconnection.

For a developer, the discipline is to treat the DPP estimate as the first credible number and everything earlier as a planning assumption. For a lender, the relevant document is the study report, not the interconnection request.

What to watch: whether MISO's expedited pathways for projects with demonstrated need change the composition of the standard cycle.

Sources

  1. 01

    Generator interconnection

    Midcontinent Independent System Operator · Planning: generator interconnection · retrieved 2026-08-08

More from Interconnection

  1. Aug 08, 202606:47 ET

    Order No. 2023 compliance filings differ on withdrawal penalties and deposits

    Transmission providers have filed cluster study frameworks under Order No. 2023. The filings set out differing deposit and withdrawal penalty structures.

    RM22-14-0004 min

  2. Aug 08, 202606:47 ET

    PJM filings set study milestones for transition cycles one and two

    PJM's filings record the closure of the serial queue and the schedule stated for the first cluster cycle.

    PJM-TC23 min

  3. Aug 05, 202607:47 ET

    CAISO Cluster 15 rules limit study capacity by zone

    CAISO tariff revisions describe zonal capacity limits applied before projects enter study.

    CAISO-C153 min

  4. Aug 04, 202604:47 ET

    SPP DISIS cycle assigns network upgrade responsibility

    SPP's tariff describes how the Definitive Interconnection System Impact Study allocates upgrade obligations among study participants.

    SPP-DRG-20253 min

Daily briefing

The dockets, read daily.

One briefing each morning: queue actions, FERC dockets, transmission and large load. Free.

Job title and region are required. They determine which segment of the briefing you receive.