Capacity interconnection rights: what a project earns by studying to deliverability
The rights, granted by some transmission providers, that permit a generator to be counted as capacity in the resource adequacy construct after passing a deliverability study.
Capacity interconnection rights are rights granted under certain regional tariffs that allow a generating facility to be counted toward resource adequacy obligations. They are earned by passing the deliverability analysis associated with the higher, network-style interconnection service, rather than by connecting alone.
The distinction is between the physical ability to inject energy and the recognised ability to be relied on at peak. A project may be interconnected and able to sell energy without holding rights that allow it to be counted as capacity, because the deliverability study tests whether its output can reach load under the conditions the tariff specifies.
Because the mechanics are regional, the definition that governs any particular project is the one in the transmission provider''s tariff. Retention on repowering, transfer on sale, and treatment when a project reduces its capacity are all tariff questions, and each is documented in filings on the record.
Questions
- Are capacity interconnection rights the same everywhere?
- No. The term and its mechanics are regional. Comparable concepts appear elsewhere under different names, and the governing definition is the one in the applicable tariff.
- Can these rights be transferred?
- Transfer and retention are governed by the tariff, and transfers are typically documented in filings that appear on the relevant docket.
Sources
- 01
Improvements to Generator Interconnection Procedures and Agreements, Order No. 2023
Federal Energy Regulatory Commission · RM22-14-000 · retrieved 2026-08-09
- 02
Pro forma Large Generator Interconnection Procedures and Large Generator Interconnection Agreement
Federal Energy Regulatory Commission · pro-forma-LGIP-LGIA · retrieved 2026-08-09