ISO New England first cluster study lists projects and identified upgrades
ISO-NE filings describe the study scope, the participating projects and the upgrades identified in the cluster.
ISO New England replaced its serial interconnection queue with a cluster study framework under its Order No. 2023 compliance filing. The region's queue is modest by comparison with PJM or MISO, which does not make the process less binding.
The constraint in New England is geographic. Offshore and northern resources connect at a limited number of viable points, and the upgrades required to move energy south and west are correspondingly concentrated. A cluster in that setting produces upgrade sets that are large relative to the projects sharing them.
Cost allocation in a small cluster is therefore volatile. The withdrawal of a single large position can move remaining projects materially, in either direction.
For an investor, the diligence question is the composition of the cluster rather than the merits of the individual project. For a state policymaker, the same arithmetic explains why procurement design and interconnection design cannot be considered separately.
What to watch: whether the first cluster completes without a restudy triggered by withdrawal.
Sources
- 01
ISO New England · System planning · retrieved 2026-08-08
More from Interconnection
- Aug 08, 202606:47 ET
Order No. 2023 compliance filings differ on withdrawal penalties and deposits
Transmission providers have filed cluster study frameworks under Order No. 2023. The filings set out differing deposit and withdrawal penalty structures.
RM22-14-0004 min
- Aug 08, 202606:47 ET
PJM filings set study milestones for transition cycles one and two
PJM's filings record the closure of the serial queue and the schedule stated for the first cluster cycle.
PJM-TC23 min
- Aug 06, 202610:47 ET
MISO Definitive Planning Phase assigns network upgrade cost estimates
MISO's tariff describes the study steps in which network upgrade cost estimates are produced for projects in the cycle.
MISO-DRPP-20253 min
- Aug 05, 202607:47 ET
CAISO Cluster 15 rules limit study capacity by zone
CAISO tariff revisions describe zonal capacity limits applied before projects enter study.
CAISO-C153 min