InterconnectionJul 27, 2026 · 05:47 ET3 min read

Filings distinguish executed interconnection agreements from energisation dates

Interconnection agreements record an obligation; energisation records service. The documents report the two stages separately.

Queue analysis concentrates on entry and exit: how many requests, how many withdrawals, how long the study. The commercially decisive interval is later, between execution of an interconnection agreement and energisation.

That interval is governed by facilities the interconnection customer does not build and cannot schedule: the transmission owner's upgrades, the substation work, the protection and control commissioning. It is also where long-lead equipment risk lands.

Public data on this interval is thin. Interconnection agreements are filed and therefore visible; energisation is usually observable only through generator inventory reporting months afterwards.

For a lender, this is the interval that consumes construction interest with no revenue against it. For a developer, it is the interval least susceptible to management effort.

This publication treats the agreement-to-energisation interval as the primary measure of interconnection performance and will track it where the underlying filings permit.

What to watch: whether any transmission provider begins publishing scheduled versus actual energisation dates.

Sources

  1. 01

    Form EIA-860M preliminary monthly electric generator inventory

    U.S. Energy Information Administration · EIA-860M · retrieved 2026-08-08

  2. 02

    eLibrary filings

    FERC · eLibrary · retrieved 2026-08-08

More from Interconnection

  1. Aug 08, 202606:47 ET

    Order No. 2023 compliance filings differ on withdrawal penalties and deposits

    Transmission providers have filed cluster study frameworks under Order No. 2023. The filings set out differing deposit and withdrawal penalty structures.

    RM22-14-0004 min

  2. Aug 08, 202606:47 ET

    PJM filings set study milestones for transition cycles one and two

    PJM's filings record the closure of the serial queue and the schedule stated for the first cluster cycle.

    PJM-TC23 min

  3. Aug 06, 202610:47 ET

    MISO Definitive Planning Phase assigns network upgrade cost estimates

    MISO's tariff describes the study steps in which network upgrade cost estimates are produced for projects in the cycle.

    MISO-DRPP-20253 min

  4. Aug 05, 202607:47 ET

    CAISO Cluster 15 rules limit study capacity by zone

    CAISO tariff revisions describe zonal capacity limits applied before projects enter study.

    CAISO-C153 min

Daily briefing

The dockets, read daily.

One briefing each morning: queue actions, FERC dockets, transmission and large load. Free.

Job title and region are required. They determine which segment of the briefing you receive.