Rulemaking that produced Order No. 1977, establishing the Commission's revised procedures for backstop siting authority for transmission facilities within National Interest Electric Transmission Corridors.

Open the filing · Order No. 1977

Coverage of this docket

  1. TransmissionAug 06, 2026

    Order No. 1977 sets FERC backstop siting procedure; DOE corridor designation sets its scope

    The order establishes application procedures. Corridor designation determines where the procedure applies.