ERCOT publishes large load interconnection requests by county and status
ERCOT's large load reporting lists requested capacity, county and status for load interconnection requests, with a publication date.
Load additions in most of the United States are visible only through utility filings and distribution planning. In ERCOT, the growth of very large single-site loads has pushed the grid operator to track and publish large load interconnection activity as a distinct category.
The disclosure is imperfect as a forecast. A request is not a commitment, and the gap between announced and energised load in this class is wide. It is nonetheless the only systematic public record of where multi-hundred-megawatt loads are seeking service in the largest single-state market.
For a planner, the signal is spatial rather than aggregate. Concentration in specific zones determines whether the constraint is generation, transmission, or transformer procurement.
For a developer of generation, the same data indicates where a load-side counterparty may be willing to contract at terms that support financing.
For a lawyer, the open question is what obligations attach to a large load at the point of curtailment, and whether the applicable protocols treat that load as interruptible in fact as well as in contract.
What to watch: any protocol revision that formalises the queue and attaches deposits or milestones to a large load request.
Sources
- 01
Electric Reliability Council of Texas · ERCOT planning · retrieved 2026-08-08
More from Load
- Jul 29, 202605:47 ET
Filings describe tariff treatment of behind-the-meter generation serving large load
The records address when on-site generation avoids an interconnection request and how grid service is charged.
NATIONAL3 min
- Jul 28, 202606:47 ET
Utility load forecasts and aggregated national projections are compiled on different bases
Reports state that customer-request-based utility forecasts, when summed, exceed national projections. The documents describe the compilation method for each.
NATIONAL3 min